Before You Sign a Commercial Lease in Dallas-Fort Worth: Walk the Space With a Contractor

By Lonnie Harrison, PresidentNovember 26, 202610 min read
An empty commercial suite with white walls, square columns, a tile floor and a suspended ceiling with light panels
An empty suite looks ready to build. The slab, the electrical service, the units on the roof and the last certificate of occupancy decide whether it is. Illustration: licensed photography, not a Harrison project.

Yes, a commercial general contractor will walk a space with you before you sign the lease, and it is the most useful hour in the whole project. On the walk the contractor checks the things that decide the build-out cost: the slab, the sewer line, the electrical service, the HVAC units, the restrooms, the fire sprinkler system and whether the city will treat your business as a change of use. You leave knowing what the space needs, and you can negotiate the lease with that in hand. At Harrison Construction this walk is the first step of our pre-construction service.

In short
  • Walk the space with a contractor before you sign, while the landlord can still agree to pay for what is missing.
  • Two suites of the same size and rent can differ widely in build-out cost because of the slab, the utilities and the HVAC.
  • In Fort Worth, a different type of business in the space needs a change of use permit before a new certificate of occupancy.
  • What the contractor finds belongs in the lease: the work letter, the allowance and the date rent starts.
  • A walk gives you a list and a conceptual estimate. Drawings turn that into a firm price.

Who will walk a commercial space with you before you sign?

Three people can look at a space with you, and each sees something different. Your broker sees the deal: rent, term and the location. Your architect sees the layout: whether your plan fits. A general contractor sees what it will take to build: what is already there, what has to be added and what that does to the budget and the opening date.

Ask a contractor who builds your kind of space. A restaurant, a dental office and a retail store put different demands on the same suite, so a contractor with restaurant finish-outs on its records knows to look for the grease interceptor, and one with dental offices knows to ask what is under the slab.

At Harrison Construction we walk spaces across Dallas-Fort Worth for owners who have not signed yet. Our records list 103 tenant finish-outs and 71 renovations, with the most projects in Dallas, Fort Worth, Plano and Arlington, so most of the centers and building types in the area are familiar ground. If you would like us to look at a space, send the address through our contact page or call (817) 988-0242.

Why the walk comes before the lease, not after

Before you sign, every problem in the space is a negotiating point. The landlord can replace an old rooftop unit, raise the tenant improvement allowance, bring a larger electrical service to the suite or give you more time before rent starts. After you sign, the same problem is a cost to you.

The walk also protects the opening date. A space that needs a new electrical service from the utility company, a grease interceptor or a change of use takes longer to open than one that does not. If the lease starts rent on a fixed date, you want to know that before you agree to it. Our guide to how long a commercial tenant finish-out takes explains what moves the schedule.

A practical stepAsk the broker for a short due-diligence period in the letter of intent, and book the contractor walk inside it. An hour in the space is enough to find the expensive items.

The ten things a contractor checks on a pre-lease walk

The table lists what we look at, in the order we usually walk a suite, and why each item matters to the lease.

What a contractor checks in a commercial space before you sign the lease

CheckWhat we look atWhy it matters before you sign
1. Delivery conditionShell, second-generation or as-is, and what the landlord’s work letter promisesDecides how much of the build is yours
2. SlabWhether it can be trenched, and whether it is post-tensionedNew drains mean cutting the slab. Cables in it have to be located first
3. Sewer and waterWhere the sewer line runs, the water line size, a grease interceptor for food serviceDistance to the sewer line sets the plumbing cost
4. Electrical serviceSize of the service, room in the panel, where the meter isAn upgrade involves the utility company and takes coordination
5. HVACAge, size and condition of the rooftop units, and who owns them under the leaseReplacement is a common landlord negotiating item
6. GasWhether gas reaches the suite and at what sizeMatters for kitchens and some water heaters
7. Restrooms and accessibilityNumber of restrooms, accessible route from the parking to the door and through the suiteUpgrades may be required when you remodel
8. Fire protectionSprinkler system, fire alarm, exitsChanges to walls and ceilings mean changes to both systems
9. Roof and structureRoof condition, whether it can carry new equipment, ceiling heightHoods, exhaust fans and new units need openings and support
10. Use and certificate of occupancyWhat the space was last used for and whether your business is the same type of useA change of use brings more review and sometimes upgrades

How to read this table: items 2 through 6 are the ones that most often separate an affordable suite from an expensive one, because they are under the floor, behind the walls or on the roof. Item 10 is the one owners most often miss, because it is on paper, not in the room.

Shell, second-generation or as-is: what you are really leasing

How the space is delivered decides how much there is to build.

  • Shell. A new or stripped suite with little more than the slab, the outside walls and the storefront. Sometimes the slab has not been poured at all. Every system is yours to build, and the landlord’s work letter says what is delivered. Our guide to finishing out a shell space in a DFW strip center covers how to read it.
  • Second-generation. A space a similar business has already used. A former restaurant may have a hood, a grease interceptor and restrooms in place. That can save a great deal, if the systems are in working order and fit your layout. Our guide to taking over a second-generation restaurant space has the checklist.
  • As-is. Whatever the last tenant left. It may be close to what you need or it may all have to come out. Demolition is a cost too.
Snappy Salads storefront with a glass curtain wall and outdoor tables
From the parking lot, most retail-center suites look alike. What differs is behind the storefront and under the slab. Snappy Salads has 6 finish-outs on the Harrison project records, in Dallas, Fort Worth, Frisco, Lewisville and Plano. Photo: Harrison Construction project gallery.

The same suite can also suit one tenant and not another. A retail store can use almost any shell. A restaurant needs gas, a path for the hood exhaust to the roof and a place for the grease interceptor. A dental office needs plumbing, vacuum and air lines under the slab at every chair. Tell the contractor what you plan to open before the walk, so the right things are checked.

The certificate of occupancy: is your business a change of use?

This is the paper side of the walk. In Fort Worth, the city’s Certificate of Occupancy page says any building used or occupied in the city must have a certificate of occupancy. What you need to get one depends on what the space was used for before.

Screenshot of the City of Fort Worth Certificate of Occupancy page with the Change of Use tab highlighted, explaining that a different type of business needs a new certificate of occupancy and a Change of Use application
The City of Fort Worth’s Certificate of Occupancy page, Change of Use tab (highlighted): a different type of business than the one now in the space needs a new certificate of occupancy, starting with a Change of Use application. Screenshot: fortworthtexas.gov, November 2026.

Fort Worth certificate of occupancy: which situation is yours

Your situationWhat the city’s page saysWhat it means for your lease
A different type of business than the one in the space nowA new certificate of occupancy is needed, through a change of use permit, with or without remodeling. Building and zoning plan review teams review it, and other groups may tooAsk for time in the lease for the review, and check the zoning before you sign
The same type of use, new owner or tenantA new certificate of occupancy can be issued on application. Documentation of the existing use is requiredAsk the landlord for the last certificate of occupancy for the suite
A shell buildingA shell building does not receive a certificate of occupancy until a separate remodel permit for a tenant finish-out is completedYour finish-out permit is the path to the first certificate for the suite

How to read this table: the first column is your situation, the second is a summary of the City of Fort Worth’s Certificate of Occupancy page as read in November 2026, and the third is what to do about it before you sign. Other cities in Dallas-Fort Worth have their own rules, so check with the city where the space is.

The city’s page also notes that, depending on the scope of work and the proposed use, inspections may be required from several departments, including building, mechanical, electrical, plumbing, fire and health. A contractor who works in the city regularly can tell you on the walk which of these your business is likely to bring.

Zoning is a separate question from the building code. Fort Worth’s permits page offers a zoning check that shows where a type of business is allowed. Run it, or ask your broker to confirm in writing that your use is allowed in the center, before the lease is final.

From the walk to a number: how the estimate works

Owners often ask for a price at the end of the walk. What a careful contractor can give at that point is a list of what the space needs and, soon after, a conceptual estimate: a budget built from the size, the use, the condition we saw and our records of similar projects.

A conceptual estimate is good enough to compare two spaces, to check the tenant improvement allowance against the real cost and to decide whether to go forward. It is not a bid. A firm price needs drawings from your architect, because the drawings fix the layout, the finishes and the equipment. Our guide on how to prepare for a commercial construction bid explains the difference and what to hand a contractor at each stage.

We do not quote a price per square foot from the sidewalk. Two suites of the same size can be far apart in cost because of the ten items in the table above. Our guide to restaurant build-out cost in Texas shows how those items drive the number for a restaurant.

What to bring to the walk

The more the contractor knows about your plan, the more the hour is worth. Bring what you have:

  • The letter of intent or draft lease, with the landlord’s work letter and the allowance.
  • The landlord’s drawings of the suite, if the broker can get them.
  • Your floor plan or a sketch, or the brand’s prototype if you are a franchisee.
  • Your equipment list, especially cooking equipment, dental chairs, imaging or anything that needs water, drains, gas or heavy power.
  • The date you want to open and the date rent starts.
  • Access to the roof and the electrical room, arranged with the property manager ahead of time.

If you are a franchisee, bring the franchisor’s construction manual. Brand standards often decide finishes and equipment before the space is chosen, and the walk can then check the space against them. Our franchise restaurant construction page explains how we work with brand standards.

How to use what the walk finds in the lease

The walk produces a short list. Each line on it is something to raise with the landlord through your broker or attorney before you sign.

  1. Landlord work. Ask the landlord to deliver what the space lacks: a working HVAC unit, a larger electrical service, a demolished and clean suite, a grease interceptor connection.
  2. Allowance. Compare the tenant improvement allowance with the conceptual estimate, and negotiate the gap while you still can.
  3. Rent start. Tie the start of rent to something you can control, and allow for the city’s review if your business is a change of use.
  4. Responsibility. Have the lease say who repairs or replaces the HVAC units and the roof during the term.
  5. Records. Ask for the last certificate of occupancy and any drawings the landlord holds.

We are builders, not attorneys, and the lease language is your attorney’s work. What we add is the facts about the space, so the people negotiating for you know what to ask for. Budget items that owners miss at this stage are covered in our guide to common budget surprises in commercial construction.

How Harrison Construction handles a pre-lease walk

Harrison Construction is a commercial general contractor in Fort Worth, founded in 2011 by Lonnie Harrison, who has more than 25 years in construction. Pre-construction is where every project of ours starts: due diligence on the space, a conceptual estimate, value engineering, a constructability review, a development schedule, bidding, subcontractor qualification and permitting.

Our records list 190 completed locations for 73 brands in 92 cities, including 123 restaurant locations, convenience stores, retail, and dental and medical offices. We are fully bonded and insured. Our office is in north Fort Worth, and we build across the area. See our Fort Worth and Dallas tenant finish-outs pages for how we work in each city, and our tenant finish-outs page for the build itself.

If you are looking at a space, call (817) 988-0242 or use our contact page before you sign. Send the address, what you plan to open and where the lease stands. We will walk it with you and tell you what it will take.

Questions owners ask

Who will walk a commercial space with me before I sign the lease in Dallas-Fort Worth?

A commercial general contractor that offers pre-construction services. Harrison Construction walks spaces across Dallas-Fort Worth for owners who have not signed yet, checks the systems that decide the build-out cost and follows up with a conceptual estimate.

What does a contractor check before I sign a commercial lease?

The delivery condition and the landlord’s work letter, the slab, the sewer and water lines, the electrical service, the HVAC units, gas, the restrooms and accessibility, the fire sprinkler and alarm systems, the roof and structure, and whether your business is a change of use for the certificate of occupancy.

Can a contractor estimate the build-out before there are drawings?

Yes, as a conceptual estimate. It is a budget built from the size, the use, the condition of the space and records of similar projects, and it is good enough to compare spaces and negotiate the allowance. A firm price needs drawings from your architect.

What is a change of use in Fort Worth?

The City of Fort Worth’s Certificate of Occupancy page says that if the proposed business is a different type of business than what currently operates in the space, a new certificate of occupancy is needed, and the process starts with a Change of Use application. Building and zoning plan review teams review it.

Does a shell space have a certificate of occupancy?

In Fort Worth, the city’s page says shell buildings do not receive a certificate of occupancy until a separate remodel permit for a tenant finish-out is completed. Your finish-out permit is the path to the first certificate for the suite.

What should I bring to a pre-lease site walk?

The letter of intent or draft lease with the work letter, the landlord’s drawings if available, your floor plan or brand prototype, your equipment list, and your target opening date. Arrange roof and electrical room access with the property manager.

What if I have already signed the lease?

The walk is still the first step. The same checks tell you what the build will take and where the budget and the schedule are at risk, so the drawings and the estimate start from the real condition of the space.

Lonnie Harrison, President of Harrison Construction
Lonnie Harrison, PresidentFounded Harrison Construction in Fort Worth in 2011. About Lonnie · (817) 988-0242
Restaurant interior with wood screens and daylight
Discuss your project

Let’s build what’s next.

Planning a new location, build-out, renovation or commercial development? Tell us about your project and we’ll help identify the next step.

What to send us

The address, the lease or letter of intent, any drawings or the brand’s prototype set, and the date you need to open. Not all of it is needed to start the conversation.

Email office@harrisonconstructionteam.com or call (817) 988-0242.

CallDiscuss your project